A group of men completes a work in 10 days, but five of them are absent and so the rest do the work in 12 days. Find the original number of Men.

Question:A group of men completes a work in 10 days, but five of them are absent and so the rest do the work in 12 days. Find the original number of Men.

1.20

2.10

3.30

4.35