Question 1: Which of the following best describes the approach for determining the iteration (timebox) length?

Iterations (timeboxes) should always be 30 days

The team determines iteration (timebox) length by dividing the total number of story points by the average velocity of the team

Iterations (timeboxes) should always be two weeks

The team should agree on the length of the iteration (timebox) taking the size and complexity of the project into consideration

Total MCQS Questions are 50 in this paper Agile Scrum Mcq Question Set 2
Search
Categories
R4R Team
R4R provides Multiple choice questions and answers ( MCQs) .The questions on R4R.co.in website is done by expert team! Mock Tests and Practice Papers for prepare yourself.. Mock Tests, Practice Papers,Agile Scrum Mcq Question Set 2, MCQS, Objetive choice questions and answers, Multiple choice questions and answers, objective, questions , answers, MCQs questions and answers