Question 1: SS dependency implies?

The work can happen in parallel and the tasks must end at the same time.

The work can overlap or proceed in parallel.

Task 1 must finish before Task 2 can start

Task 2 must finish before Task 1 can start

Total MCQS Questions are 58 in this paper Microsoft Project MCQ Set 2
Search
Categories
R4R Team
R4R provides Microsoft Flow Multiple choice questions and answers (Microsoft Flow MCQs) .The questions on R4R.co.in website is done by expert team! Mock Tests and Practice Papers for prepare yourself.. Mock Tests, Practice Papers,Microsoft Project MCQ Set 2,Microsoft Flow MCQS,Microsoft Flow Objetive choice questions and answers,Microsoft Flow Multiple choice questions and answers,Microsoft Flow objective, Microsoft Flow questions , Microsoft Flow answers,Microsoft Flow MCQs questions and answers