The latest finish time for an activity:

Question: The latest finish time for an activity:

1.Equals the min. of LFT − t for all immediate successors

2. Equals the max. of LFT − t for all immediate predecessors.

3.Equals the max. of EST + t for all immediate predecessors.

4.Equals the min. of EST + t for all immediate successors.