The cost impact of a risk event occurring as a project proceeds through its life cycle tends to

Question:The cost impact of a risk event occurring as a project proceeds through its life cycle tends to

1.Slowly rise

2.Slowly drop

3.Drop sharply and then level out

4.Rise sharply and then level out