During which stage of Risk planning are modeling techniques used to determine overall effects of risks on project objectives for high probability, high impact risks?

Question:During which stage of Risk planning are modeling techniques used to determine overall effects of risks on project objectives for high probability, high impact risks?

1.Identify Risks

2.Plan Risk responses

3. Perform Qualitative risk analysis

4.Perform Quantitative risk analysis