A can do a piece of work in 4 days. B can do it in 5 days. With the assistance of C they completed the work in 2 days. Find in how many days can C alone do it?

Question: A can do a piece of work in 4 days. B can do it in 5 days. With the assistance of C they completed the work in 2 days. Find in how many days can C alone do it?

1.10 days

2.20 days

3.5 days

4.4 days