A can do a piece of work in 30 days. He works at it for 5 days and then B finishes it in 20 days. In what time can A and B together it?
Home
Question:A can do a piece of work in 30 days. He works at it for 5 days and then B finishes it in 20 days. In what time can A and B together it?
1.16 2/3 days
2.13 1/3 days
3. 17 1/3 days
4.16 1/2 days
Show Answer
Answer:2