A can do a piece of work in 40 days; B can do the same in 30 days. A started alone but left the work after 10 days, then B worked at it for 10 days. C finished the remaining work in 10 days. C alone can do the whole work in?

Question:A can do a piece of work in 40 days; B can do the same in 30 days. A started alone but left the work after 10 days, then B worked at it for 10 days. C finished the remaining work in 10 days. C alone can do the whole work in?

1.24 days

2.30 days

3.44 days

4.17 1/2 days