R4R.CO.IN
About
Services
Contact
A and B can do a piece of work in 7 days. With the help of C they finish the work in 5 days. C alone can do that piece of work in?
Home
Question: A and B can do a piece of work in 7 days. With the help of C they finish the work in 5 days. C alone can do that piece of work in?
1.1 days
2.10 days
3.30 days
4.32 days
Show Answer
Answer:3
← Older
Newer →
Search
Go!
R4R Team
R4Rin Top Tutorials are Core Java,Hibernate ,Spring,Sturts.The content on R4R.in website is done by expert team not only with the help of books but along with the strong professional knowledge in all context like coding,designing, marketing,etc!