A can do a piece of work in 10 days and B can do it in 15 days and C can do it 20 days. They started the work together and A leaves after 2 days and B leaves after 4 days from the beginning. How long will work lost?
Question: A can do a piece of work in 10 days and B can do it in 15 days and C can do it 20 days. They started the work together and A leaves after 2 days and B leaves after 4 days from the beginning. How long will work lost?