A can do a piece of work in 21 days and B in 28 days. Together they started the work and B left after 4 days. In how many days can A alone do the remaining work?

Question:A can do a piece of work in 21 days and B in 28 days. Together they started the work and B left after 4 days. In how many days can A alone do the remaining work?

1.12

2.10

3.16

4.14