Twenty four men can do a work in 35 days. How many men are required to complete the work in 21 days?

Question:Twenty four men can do a work in 35 days. How many men are required to complete the work in 21 days?

1.38

2.40

3.36

4.42


Search
R4R Team
R4Rin Top Tutorials are Core Java,Hibernate ,Spring,Sturts.The content on R4R.in website is done by expert team not only with the help of books but along with the strong professional knowledge in all context like coding,designing, marketing,etc!