Sreedhar and Sravan together can do a work in 25 days. With the help of Pavan, they completed the work in 8 days and earned Rs. 225. What is the share of Sravan, if Sreedhar alone can do the work in 75 days
Question:Sreedhar and Sravan together can do a work in 25 days. With the help of Pavan, they completed the work in 8 days and earned Rs. 225. What is the share of Sravan, if Sreedhar alone can do the work in 75 days