A can do (1/3) of a work in 5 days and B can do (2/5) of the work in 10 days. In how many days both A and B together can do the work?
Home
Question:A can do (1/3) of a work in 5 days and B can do (2/5) of the work in 10 days. In how many days both A and B together can do the work?
1.7 ¾
2.4/5
3.3/8
4.10
Show Answer
Answer:3