You are working on a project schedule. You need two tasks to end at the same time so that your review team can do their work on both tasks. Which link type is appropriate?

Question:You are working on a project schedule. You need two tasks to end at the same time so that your review team can do their work on both tasks. Which link type is appropriate?

1.Start-to-Start (SS)

2.Finish-to-Start (FS)

3.Start-to-Finish (SF)

4.Finish-to-Finish (FF)