The _______ is the longest duration of linked tasks in a project which must be completed on time for the project to complete on time.
Home
Question:The _______ is the longest duration of linked tasks in a project which must be completed on time for the project to complete on time.
1.critical path
2.lead time
3.lag
4.schedule variance
Show Answer
Answer:1