Putting 9FF3 in the predecessor column of task 10 causes which of the following to happen?

Question:Putting 9FF3 in the predecessor column of task 10 causes which of the following to happen?

1.Task 9 finish three days after task 10 finishes

2.Task 8 to complete three days after Task 9

3.Task 3 to complete nine days before Task 4

4.Task 10 complete three days after task 9 completes


Search
R4R Team
R4Rin Top Tutorials are Core Java,Hibernate ,Spring,Sturts.The content on R4R.in website is done by expert team not only with the help of books but along with the strong professional knowledge in all context like coding,designing, marketing,etc!