SF dependency implies?

Question:SF dependency implies?

1.Task 2 must finish before Task 1 can start

2.Task 1 must finish before Task 2 can start

3.The work can happen in parallel and the tasks must end at the same time.

4.The work can overlap or proceed in parallel