The critical path method calculates theoretical early start and late start and finish dates. Critical path have either

Question:The critical path method calculates theoretical early start and late start and finish dates. Critical path have either

1.Positive Total Float

2.Positive or Negative Total Float

3.Zero or Negative Total Float

4.Zero or Negative Total Float