After "Pour the Foundation" and "Build the Frame" are both finished, "Mount the Drywall" should start immediately. To put these task relationships in your plan, which dependency types should you create?

Question:After "Pour the Foundation" and "Build the Frame" are both finished, "Mount the Drywall" should start immediately. To put these task relationships in your plan, which dependency types should you create?

1."Pour the Foundation" Finish-to-Finish with "Build the Frame," and "Mount the Drywall" Finish-to-Start with "Pour the Foundation."

2.Pour the Foundation" Start-to-Start with "Build the Frame," and "Mount the Drywall" Finish-to-Start with "Pour the Foundation."

3."Pour the Foundation" Finish-to-Start with "Build the Frame," and "Build the Frame" Finish-to-Start with "Mount the Drywall"

4.Pour the Foundation" Finish-to-Start with "Build the Frame," and "Build the Frame" Finish-to-Start with "Mount the Drywall"