When two tasks have an FS dependency, but the work can overlap or be done in parallel, how can you reduce the overall duration of the project?

Question:When two tasks have an FS dependency, but the work can overlap or be done in parallel, how can you reduce the overall duration of the project?

1.Change their dependency to SF

2.Change their dependency to FF

3.Move the deadline forward so that participants work faster.

4.Chance their dependency to SS