If a task is ______, as resources are added or removed on the assignment, the work remains constant and is redistributed among the resources.
Home
Question:If a task is ______, as resources are added or removed on the assignment, the work remains constant and is redistributed among the resources.
1.ahead of schedule
2.effort-driven
3.work-driven
4.behind schedule
Show Answer
Answer:2