On the Task tab, the _____ group provides buttons to mark the percent complete, link tasks to one another, and inactivate a task.

Question:On the Task tab, the _____ group provides buttons to mark the percent complete, link tasks to one another, and inactivate a task.

1.Task

2.Data

3.Properties

4.Schedule