Where can you set fixed duration, effort driven, and manually scheduled?
Home
Question:Where can you set fixed duration, effort driven, and manually scheduled?
1.Team Planner
2.Resource Sheet
3.Project Information dialog box
4.Task form
Show Answer
Answer:4