In testing a pile by load test, pile platform is loaded with one and half times the design load and a maximum settlement is noted The load is gradually removed and the consequent rebound is measured For a safe pile, the net settlement (ie total settlement minus rebound) per tonne of test load should not exceed

Question:In testing a pile by load test, pile platform is loaded with one and half times the design load and a maximum settlement is noted The load is gradually removed and the consequent rebound is measured For a safe pile, the net settlement (ie total settlement minus rebound) per tonne of test load should not exceed

1.10 mm

2.15 mm

3.20 mm

4.25 mm