You are the project manager on the installation of a new ERP system. Before the system can be installed on the company's servers, the operating system must be upgraded. This is an example of what type of precedence relationship?
Question:You are the project manager on the installation of a new ERP system. Before the system can be installed on the company's servers, the operating system must be upgraded. This is an example of what type of precedence relationship?