How does Microsoft Project calculate the total work time of a summary task?

Question:How does Microsoft Project calculate the total work time of a summary task?

1.Time between the earliest start date and the latest finish date of its subtasks.

2.Total work time is not specified on summary tasks

3.Sum the work time of all subtasks.

4.Total work time of the longest subtask.