How much should CPI and SPI be in a project ahead of schedule and costs?

Question:How much should CPI and SPI be in a project ahead of schedule and costs?

1.CPI <1; SPI<1

2.CPI >1, SPI >1

3.CPI<1 : SPI>1

4.CPI>1 ;SPI<1