How much should CPI and SPI be in a project ahead of schedule and costs?
Home
Question:How much should CPI and SPI be in a project ahead of schedule and costs?
1.CPI <1; SPI<1
2.CPI >1, SPI >1
3.CPI<1 : SPI>1
4.CPI>1 ;SPI<1
Show Answer
Answer:2