Which of the following is the best way to resolve an issue in which a resource is overallocated?

Question:Which of the following is the best way to resolve an issue in which a resource is overallocated?

1.Removing that resource from another task

2.Changing the resource's availability from 50% to 100%

3.It cannot be resolved.

4.Adding another resource to the task