You would like to understand which tasks are critical and which are not. When looking at the Gantt chart, how are these tasks identified by default?

Question:You would like to understand which tasks are critical and which are not. When looking at the Gantt chart, how are these tasks identified by default?

1.Critical tasks are indicated in red and other tasks are indicated in blue.

2.Critical tasks are indicated in dark blue end other tasks are indicated in light blue.

3.Critical tasks are indicated in a report while the Gantt chart indicates all tasks in blue.

4.Critical tasks are indicated with an icon and other tasks are indicated in blue.