You are working on a project that has tasks with no flexibility. Which constraint type offers no flexibility?
Home
Question:You are working on a project that has tasks with no flexibility. Which constraint type offers no flexibility?
1.Must Finish On
2.Start No Earlier Than
3.As Soon As Possible
4.Finish No Earlier Than
Show Answer
Answer:1